The developer's warranty in Israel after an apartment is handed over consists of two periods under the Sale of Apartments Law of 1973: a defect period (tkufat bedek), whose length depends on the type of defect, and a warranty period (tkufat achrayut) of another 3 years after it. During the defect period the developer repairs a defect unless it proves the buyer caused it; during the warranty period — if the buyer proves the cause was design, workmanship or materials. Repair demands are made in writing; if the developer does not repair, you can repair at its expense, complain to the Registrar of Contractors and go to court.

Two periods: the defect period and the warranty period

  1. The defect period (tkufat bedek) starts on the day the apartment is handed over. If a defect is found during this time, the developer is responsible for it unless it proves the defect was caused by the buyer. Contractors often talk about a "defect year" (shnat bedek), but the law has no single year: the length depends on the type of defect.
  2. The warranty period (tkufat achrayut) is 3 years after the defect period ends. The developer is still responsible, but now the buyer has to prove that the defect was caused by design, workmanship or materials.

For structural defects — load-bearing elements, the stability and safety of the building — the defect period is 20 years from handover. After that the developer is still liable if the buyer proves the defect was caused by design, workmanship or materials.

This liability cannot be reduced by contract, even with the buyer's consent; it can only be changed in the buyer's favour.

Defect periods by type of defect

Type of defectDefect period
Any other non-conformity, except structural ones and those listed below1 year
Metal and carpentry products, including aluminium and plastic2 years
Interior flooring and wall cladding2 years
Machinery and water heaters3 years
Yard development3 years
Thermal insulation3 years
Pipes — water, heating, gutters, drainage and sewage, including leaks4 years
Building waterproofing4 years
Cracks wider than 1.5 mm in non-load-bearing elements5 years
Detachment or crumbling of exterior cladding7 years
Structural defect: load-bearing elements, stability and safety of the building20 years
← swipe the table sideways →

These periods apply to contracts signed from 06.04.2011; earlier deals are covered by a previous table with different periods. If the apartment is resold, the remaining periods pass to the next buyer.

How to demand repairs: in writing and on time

  1. Document the defect. Photos, the date you found it, exactly where it is and how it shows. For leaks, damp and cracks, an engineer's opinion helps.
  2. Write to the developer. A written request is a required step before a complaint to the Registrar and your main proof that you notified in time. In the letter, give the address and apartment number, the handover date, the list of defects with photos and when each was found, and ask for a repair date. Send it in a way that leaves proof of receipt, and keep copies.
  3. Meet the notice deadline. A defect that could have been seen at handover must be reported within a year of handover. A hidden one — within a reasonable time after it is discovered.
  4. Give the developer a chance to repair. The law requires you to give the developer a fair opportunity to repair, and the developer must do it within a reasonable time.
  5. Keep a log. Record the dates of your requests, technicians' visits and the developer's answers: if the defect comes back, you will need to show when you reported it and how many times it has already been repaired.

The law sets no fixed number of days for a response. A court in Haifa interpreted "reasonable time" as the time another contractor would need to do the repair, and held that a developer who wants to repair itself must give such repairs priority.

If the developer does not repair

  • Repair at the developer's expense. If the defect has come back after one or more repairs within 2 years of your notice, or the repair is urgent and the developer has not done it within a reasonable time, the buyer may repair it and the developer bears the cost. A developer who misses the reasonable time loses the right to repair itself, even if the buyer's repair costs more.
  • A complaint to the Registrar of Contractors. It is filed online through the Ministry of Construction and Housing, and only after a written request to the developer. The Registrar handles building defects, damp, unfinished work and breaches of contract, but not monetary disputes or matters already before a court. It is a disciplinary procedure, not arbitration: you cannot obtain a repair or money through it.
  • A lawsuit. To force a repair or obtain compensation you need to sue; the claim is filed with the contract, the specification, the correspondence and an expert opinion. At this stage it is worth working with a lawyer.

If the developer makes a repair conditional on signing away other claims, that waiver is void, even in writing.

The building's common property

Defects in the lobby, roof, parking and yard are also the developer's responsibility; the defect period for yard development is 3 years. A complaint to the Registrar of Contractors about common property can be filed only by the house committee elected under the building's bylaws, so it pays for neighbours to combine defects into one request. How to record the apartment's condition on handover day is covered in the guide to accepting an apartment from the developer.

Frequently asked questions

When does the developer's warranty start?

At handover: on that day the defect period starts for every type of defect. The warranty period — another 3 years — starts when the defect period ends.

How many years of warranty are there for leaks?

For pipes, including leaks, and for building waterproofing the defect period is 4 years from handover. It is followed by the warranty period — 3 years, but then the buyer has to prove the cause of the defect.

Is it true that the warranty is a single "defect year"?

No. One year is the defect period only for other non-conformities that do not fall into a separate category. For carpentry and flooring it is 2 years, for pipes and waterproofing 4 years, for exterior cladding 7 years, for the structure 20 years.

I bought the apartment from its first owner — does the developer's warranty still apply?

Yes. The remaining defect and warranty periods pass to the next buyer. They are still counted from the date the apartment was first handed over.

How long can the developer drag out a repair?

The law speaks of a "reasonable time" and sets no number of days. If the repair is urgent and was not done within a reasonable time, or the defect came back after a repair within 2 years of the notice, the buyer may repair it at the developer's expense.

Can I get money instead of a repair?

If the developer did not repair within a reasonable time, it loses the right to repair itself and must cover the cost of the repair. A dispute over the amount is decided by a court — the Registrar of Contractors does not handle monetary disputes. Before suing, it is worth showing the case to a lawyer.

The developer asks me to sign that I have no further claims — what then?

A waiver of the right to have defects repaired is void, even in writing, if the developer made it a condition for a repair or for handing over the apartment. Sign only a confirmation of a specific repair that has been done.