APPartment
Guides

Accepting a new apartment from the developer in Israel: what to check and record

APPartment·16 November 2026·updated 16 November 2026

Accepting a new apartment from the developer in Israel means inspecting it before you get the keys; at the end, both sides sign a handover protocol (protocol mesira) that lists every defect. Signing the protocol does not take away your right to demand repairs: your rights are set by the Sale of Apartments Law of 1973 (chok ha-mecher), not by the developer's wording. Below: what to prepare, who inspects, what to check area by area, how to write the protocol, and which deadlines start running on handover day.

When the handover takes place and what to prepare

The developer sets the handover date within the deadline in the contract. If the apartment has not been handed over a month after the contractual date, you are entitled to compensation without proving any loss, tied to the rent of a comparable apartment — details in the guide to the contract with the developer.

Before the visit, gather:

  • The specification (mifrat) and the maintenance and use instructions. Under the Sale of Apartments Law the developer attaches them to the contract; if the details for the instructions were not yet known, they may be handed over together with the apartment. The law treats failure to provide the instructions as a breach of the seller's obligations. At handover, the apartment is compared against the specification.
  • A copy of Form 4 (tofes 4). This is the approval under section 157a of the Planning and Building Law on which connecting the building to electricity, water and telephone depends.
  • A home inspection engineer (bedek bayit) — agree in advance which inspection they will attend.
  • A checklist, a phone for photos, a tape measure and a spirit level — for your own check.

If the developer holds a preliminary walkthrough before the key handover, bring the inspector to that one: the developer will still have time to fix defects before you move in.

Who inspects: you or an inspection engineer

The law does not require buyers to hire a professional, but the most expensive defects are invisible to the eye. An inspection engineer comes with measuring equipment and prepares a report with photos and a list of deviations from the specification, official standards and building regulations. The report becomes the basis for your repair demand and, if it comes to a dispute, for a lawsuit.

What to keep in mind when choosing one:

  • not every report qualifies as an expert opinion for court — ask in advance whether the inspector prepares such an opinion;
  • waterproofing and drainage defects often appear only after the apartment is in use, so they are checked with instruments;
  • electrical and safety checks are done by licensed professionals;
  • some developers do not allow an inspector at the signing of the key handover protocol — find out in advance and agree in writing.

What to check: a list by area

  • The whole apartment against the specification: flooring, doors, windows, sanitary fittings, electrical, water and air-conditioning points in the right places; the parking space and storage room are the ones named in the contract. Even a small difference can be a non-conformity with the contract with financial consequences.
  • Walls, ceilings, floors: cracks, damaged tiles, height differences between tiles, damp stains, unfinished paint. Pay special attention to wall-floor joints, areas around windows, the bathroom, toilet and kitchen.
  • Water and sewage: open every tap, check water pressure, toilet flushing and drainage in sinks and the shower; look for moisture, leaks and standing water.
  • Windows, doors, shutters (trisim): they open and close without effort, glass and frames are undamaged.
  • Safe room (mamad): the heavy door and the steel window shutter close tightly and do not stick.
  • Balconies and yard: water flows to the drain, not towards the wall.
  • Electricity, gas, water heater, air conditioning: leave testing under load to a licensed professional.
  • Common property: lobby, elevator, parking, yard. The developer is responsible for these too; a complaint to the Registrar of Contractors about common property can be filed only by the house committee.

The handover protocol: what to record and what not to sign

The handover protocol records the condition of the apartment and its defects on handover day. If a dispute arises later, it will be one of the pieces of evidence, so:

  1. Record each defect separately and precisely: where, what and how extensive — "damaged tile at the balcony door", not just "tiles".
  2. Photograph every defect and keep the photos yourself.
  3. Ask for the protocol to state what repair is needed and by when it will be done.
  4. Take a signed copy.
  5. Do not sign general statements such as "I have no claims against the developer".

Signing the protocol does not in itself waive your right to repairs. Moreover, a buyer's waiver of the right to have defects repaired or to compensation for delay is void, even in writing, if the developer made it a condition for handing over the apartment or for repairs.

After handover: which deadlines start running

Handover starts the defect period (tkufat bedek): the developer repairs a defect found during this period unless it proves the buyer caused it. Its length depends on the type of defect — from 1 year for other non-conformities up to 7 years for detached exterior cladding; pipes, leaks and building waterproofing get 4 years. For structural defects the defect period is 20 years. After it comes the warranty period (tkufat achrayut) — another 3 years. The full table and how to file demands are in the guide to the developer's warranty after handover.

A defect that was visible at handover but did not make it into the protocol is not lost: you must notify the developer of it within a year of handover. For a hidden defect — within a reasonable time after it is discovered. You must give the developer an opportunity to repair, and the developer must do so within a reasonable time.

One more deadline: the developer must register the buyer's rights in the Condominium Register no later than 6 months after the building is registered or after the apartment is handed over, whichever is later.

Frequently asked questions

Should I sign the protocol if I found defects?

Usually yes: the protocol exists precisely to record defects. Signing a protocol that lists defects does not take away your right to demand their repair. Just do not sign general statements that you have no claims.

The developer will hand over keys only if I sign "no claims" — is that legal?

Such a waiver has no force: under the Sale of Apartments Law, a buyer's waiver of the right to have defects repaired or to compensation for delay is void, even in writing, if the developer made it a condition for handing over the apartment. Keep the correspondence and show it to a lawyer.

When should I bring the inspector — to the preliminary walkthrough or to the key handover?

Preferably to the first walkthrough, if there is one: the developer will have time to fix defects before you move in. At the key handover you can check what has been fixed. If the developer does not allow an inspector, find out in advance.

What if a defect turns up after I have moved in?

Notify the developer in writing and keep a copy. If the defect could have been seen at handover, you must notify within a year of the handover date; if it was hidden — within a reasonable time after discovery. From then on the defect periods for each type of defect apply.

Can I refuse to accept an apartment with defects?

It depends on the contract and on how serious the defects are, and it is better to settle such a question with a lawyer before the handover date. Minor defects are usually recorded in the protocol and the apartment is accepted: the right to repairs is preserved. Separately, check whether Form 4 has been issued.

Is the developer also responsible for the lobby, yard and parking?

Yes, common property is also the developer's responsibility: for example, the defect period for yard development is 3 years. Claims about common property are collected by the house committee — only it can file a complaint about common property with the Registrar of Contractors.